Sunday, April 18, 2010

Splitting Wood


A neighbor generously lent me his wood splitter for a few weeks.

Before I could start splitting any wood, I needed to clean up the area where the wood would be stacked.
There were stacks of bricks all around the kiln yard. I had to get more organized!

Hard bricks can always be used someplace, so were stacked together, out of the way. Not really too many of those left. Of the remaining soft bricks, many had dried mortar on them, and there were chunks of the arch. In the right photo, you can see 16 double-paper, grocery bags of soft bricks. The dry mortar just chips a chunk out of the brick when trying to remove it, so those bricks are 'toast', trash, unusable. Unless someone wants to grind them down to grog. A big, labor-intensive job, and only worth it if you can use the grog, as for kiln insulation.
And more trash, like rain-damaged cardboard boxes that used to hold bricks.

In the first photo is the result of about an hour-and-a-half of splitting wood.
I stacked it later, and think it is about 1/8 a cord. I need to pick up my pace, and/or find someone to help split wood. I did get an offer from someone, I just find it hard to ask someone to come over to do very hard labor. I have to get past that.
There is a variety of wood that I had accumulated last fall. Already, I've split redwood, fir, oak and pine limbs. Such a variety of wood for the pots. Sometime, it might be useful to fire with just one type of wood, to determine the effects of each wood. This first wood-fire will be using what I have scavenged/saved.

Thursday, March 18, 2010

Pots from the first firing












Here are photos of some of the pots from the first firing of my new kiln.
Fueled by propane, most of the glazes appear much different than from my old kiln.

One reason would be the reduction atmosphere was greatly increased. While back-pressure could be observed from the top & middle peep holes during the firing, how much reduction is only relative to previous observations.

The set of nested bowls in the last pic is a good example: The glaze inside the bowls has 3% copper that usually comes out of a fire appearing celadon-colored, sometimes splashed red or violet. This time it came out blue. I'm not complaining at all, but I was very surprised.

The bowl directly above it was a re-fire, of a black & white bowl that was not interesting at all. In the increased reduction atmosphere, the colors have flowed & copper migrated into a beautiful result. (In my opinion.)

There was only one bowl whose glaze ran onto a shelf. Although there were a number of pots that were under-fired, they can be re-fired a later time. It was strange to see pots with under-fired glaze on the same shelf as those with mature glazes - even the same glaze.

Howard & I had much discussion as each shelf was unloaded. His opinion of the result & my observation of what I expected. We made significant change to the design of the bag wall.
The next firing will be mostly wood-fueled, and with the bag wall change, should result in a much more even firing.
This firing had to go slow to dry out the mortar & bricks, check the bag wall design, and check for any major air leaks. I am very pleased with the results and the kiln.

I look forward to the next firing - the first wood-fueled firing of my new kiln.
There is much wood-splitting & stacking to be done. I absolutely have to get a handle on how much wood it will take to fire this kiln. Stay tuned....

Tuesday, March 16, 2010

Opening the Kiln


The kiln took quite a few days to cool, as hard bricks hold heat a long time.
Firing was on Wednesday, Thursday everything was still very hot. Fri, Sat & Sunday, I worked at the winery. (I have a part-time job at a winery tasting room/art gallery just 3 miles down the road from me.)

Each day, I opened the kiln a little more. Friday, it was cracking the dampers and removing kaowool from the burner openings. I also removed the door frame of 2" thick kaowool that super-insulated the bricked-up door. Saturday morning, I checked the temperature inside the kiln with the pyrometer, and found it was down to 700 degrees F. I could safely remove the 3 peep hole plugs on the front & back for a final cooling. It wouldn't be until Monday that I had time to take down the brick door. Monday was a beautiful, warm, sunny day - very different from the intense cold and showers of the previous week. I had to wait til dusk to take the photo you see on the above left, as the sunlight across the bottom half of the kiln washed any picture-taking with my digital camera.

The piece on the right was contributed by my friend Bob. He brought over a half dozen pieces that he sprayed an ash glaze on. The ones I have seen turned out great. What was that glaze recipe again? I'd like to use it on more pieces, next firing.

In the meantime, on the day the kiln was fired, I caught a nasty headcold that is still hanging on a week later. I also got a (fortunately, very mild) case of poison oak on my face and neck. During one of the lulls on firing-the-kiln-day, I decided to get my electric chain saw out & start cutting some of the branches from the wood pile near the kiln. I remember using a gloved hand to turn up the collar on my down vest, and wipe my running nose. Will I ever learn to not touch my body after touching oak rounds? I did toss a few small pieces of wood into the firing kiln, but we decided the wood was not dry enough to make any contribution, so it got re-covered for the next firing. Never a dull moment.

Howard is due here tomorrow, Wednesday, to show me how to remove the delicate thermocouples from the burners until the next firing. Perhaps I'll get the first stack of shelves unloaded so we can see the middle stack of pots and draw conclusions from the first firing.

So far, I've seen there was very good reduction in the kiln, the colors are incredible. To my surprise, the colors turned out different than they used to in my old kiln. I will photograph & post these soon. The inside of the kiln is beautiful! The hard bricks are a toasty brown. You can see a large vase in the upper left of the front stack. It was in the kiln as a place-holder, a cracked piece of stoneware that I kept around just because I always liked the shape. It turned out a beautiful light brown. I'm pleased with the pots I've been able to see, and look forward to the others.

First Firing












All the anticipation & preparation for this - and it is finally happening.
I could barely contain myself. I worked long days glazing and loading the kiln, preparing for Howard to come over and set the burners so we could finally light the fire.

While I bricked up the door, first with hard bricks facing the inside of the kiln, then with soft bricks backing up, Howard set the burners. If you look closely at the middle photo, you can see a thin wire behind (to the right) the burner, which attaches to a thermocouple that rests next to the hot end of the burner (in the far left photo, it peeks through a hole in a side "arm" of the burner. The thermocouple is a safety, that needs to "sense" the flame coming from the burner. If anything ( say, a gust of air) were to blow the burner out, the thermocouple stops the flow of propane. Thus preventing a build-up of highly flammable gas.

After lighting the burners, it took a while to keep the flame very low, yet still lit. We needed to slowly dry out the mortar in the kiln. The weather had been cool and damp all winter, and a lot of moisture had accumulated in the bricks. This was the plan for overnight. A storm was blowing in, and an old door was moved in front of the burner as a windbreak. The burner on the opposite side was safe from incoming breezes.
Once all was set, Howard's partner Deborah, surprised me with a picnic & bottle of wine to "launch the kiln". We toasted the first firing.

I checked the kiln overnight, all was fine, no burners had been blown out. Early the next morning, I slowly turned up the gas. We kept the firing slow as the kiln was steaming heavily. Howard didn't come over until late morning. He wanted to be on hand as we took on the challenge of getting to desired temperature from top-to-bottom and side-to-side.

The photo on the far left is looking through the kiln from one burner hole to the other. When the gas is turned up, it is quite a view to be able to see the glow emitted from the maw of a burner.
On the right-side photo are me & Howard, the kiln guru.

It was a long day and evening, as Howard & I discussed whys & wherefores of kilns and firing. And why I wanted the dampers in, so my glazes would come out as I desired, even though it took much longer to fire that way. About 9:30pm, as the both of us were physically & mentally exhausted we decided the firing was done. Cone 10 was "touching down" in the middle of the back side. Not wanting to over-fire (under-fired pots can always be re-fired, but once they are too hot, it is too late for the pots) the middle of the kiln a usual hot spot, we shut down.

Friday, March 12, 2010

Loading the kiln















First pic shows the bag wall design. The bottom 2 rows of the bag wall are mortared in. I kept the vertical bricks & horizontals above loose for this firing, so I can adjust for the next firing if desired.

Half bricks were used under the bottom shelves, to give a 4.5" rise off the kiln floor.

Cone packs, that indicate how hot the kiln gets at a particular site in the kiln, were in front of each of the 6 peep holes, and an additional dozen were scattered around the kiln, including the floor and bagwall.

The next 3 photos are the back, middle & front stacks of shelves.
I had mis-judged just how much larger this kiln is than my last kiln.
A friend had brought over some pots a few days previous to add to this firing. I still ended up bringing some pots from the "archives" to be re-fired, in an effort to fire a full kiln.

One thing I didn't discover until I was stacking the front shelves was this: Since I had to turn the kiln shelves sideways to get them through the doorway, there was a limit as to how high I could put the top shelf in front. I will have to make sure I have at least a kiln shelf of taller pieces for every kiln load fired.

Tuesday, March 9, 2010

Loading the kiln











These are some of the last preparations before loading pots into the kiln:
Right pic is 2" of kaowool over the arch and on the door frame.
I had planned on tying porcelain buttons onto the door with nichrome wire, but found that by cutting the kaowool 1/2" wider than needed, it just eases into the frame and stays there with pressure.

If you look carefully at the left pic, you can see the dampers in horizontal position.
There is one on each side of the chimney, and they are stark white.
I had a mullite electric kiln shelf cut into pieces that would fit the damper openings.

Next post will show loading the kiln.
The firing is so close, I can taste it.
I saved cleaning 2/3 of the kiln shelves for this morning. Had figured the exercise would keep me warm in the cool morning. Just looked outside, and it is 28 degrees out there! I'm hoping it warms up at least 10 degrees while I eat breakfast.

Sunday, February 28, 2010

Finishing touches















I'm ba-ack! Went to Mexico for a couple of weeks of warmth (even the rain is warm there).

These photos show what was completed before I left:
First photo on the left is the chimney with its rain/bird cap. The same person who set the chimney bricks above the roof set the cinder blocks in front of the kiln door. He sure does good work, and fast. On the right is a photo of the B-4 propane burners with baso valves (safetiesa: in case the gas blows out when pre-heating overnight, the baso valve will shut the gas off entirely). The person at the propane company was quite impressed with the burner set-up that I showed when I went to purchase the rubber gas lines. This is Howard's work - but I now understand what is entailed to put it all together.

Before leaving, I wanted to finish making pots for the first firing. Sure enough, I was attaching handles & feet to mini-pots hours before leaving for the plane. Got them all done, too.

Wednesday, January 20, 2010

Some last touches


Today a few items got tied up on the kiln.

Photo on the left shows the pipes/plumbing for the propane. Yesterday, I met Howard at Lowe's to select the black iron nipples, bell reducers, tee's, an elbow and a cross. We laid out the pieces we wanted on the floor to make sure they were all there. Did very good, too, as there was one iron nipple left-over.

The green thingy is a pressure reducer for my raku kiln. My old gas kiln ran on low-pressure propane burners, the new kiln will run on hi-pressure propane burners. All the connections between the propane tank and the kiln burners themselves had been like a "black box" to my brain. The parts needed to get propane from point A to point B was a big mystery to me. I don't begin to "know it all" at this time, but I have greatly improved my understanding of how & why one uses particular pieces to "plumb" a kiln. And the raku kiln is now operable!

On the right side photo, the angle-iron braces on the sides of the upper chimney were installed today. The original design called for the braces to be longer, but they didn't fit with the rain flashing on the chimney above the roof. So we had Claude cut the angle-iron, and it was reconfigured as pictured above. Threaded tie rods go around the chimney at the top & bottom of the metal braces.

Time to go back to making pots - there's nearly enough for the first firing...

Kiln Door & more


The short story is the photo on the right. Soft bricks were mortared next to the corbelled chimney bricks and against the kiln wall. This is the only place on the side walls that did not have kaowool (fiber insulation) for added insulation.

On the left, is a brick-up of the kiln entrance. Hard bricks are next to the hot-face interior of the kiln, and soft bricks are the back-up layer. If you look close, you can see that I ran out of soft bricks half way up the doorway. I still have some soft bricks, but they all need to be mortared together. That means they are halves (or in more pieces). It took many tries of bricks going up and down to come up with what is pictured. To get the peep holes in position to line up with the holes cut in the sheet-metal/kaowool door cover was one obstacle.

I had not planned for the number of half bricks I would need in the door. Renting a brick saw, hauling it out here, then back to town just to cut a small number of bricks seemed like over-kill and a lot of time spent for a little amount to get done. Sutherlin Rentals was open on Monday's holiday, and consented to let me bring my bricks in to be cut. They knew me from previous rentals, and set up the brick saw in back. It didn't take me long to cut the bricks I needed (and a few spares). Not watching the time, I can't say for sure, but I'm sure it was not more than 15 minutes.

Thursday, January 14, 2010


Today, a brick mason, Randy, came to help me finish the chimney. He could definitely lay bricks much faster than I could. I learned a few brick-laying tricks now - at the end of my brick-laying.

The rain flashing as the chimney came through the roof seemed to be the greatest challenge to me. Randy knew what to do. We had many discussions, as I wanted to have much more air through the roof next to the chimney. Claude brought a can of spray rust-o-leum primer to protect the galvanized metal rain flashing.

The chimney now rises at least 24" above the roof. We ended up placing a board weighted down with a couple of bricks on top of the chimney to prevent rain from coming down the hole.

I keep making a few more pots for the kiln...

Saturday, January 2, 2010

Out of Mortar - Again


Thursday & Friday (New Year's Eve & Day) the chimney got mortared to within 10 rows of the kiln shed roof. The top row of bricks has only 3 of the 7 bricks mortared before the mortar ran out.

See how much higher than the blue ladder the chimney goes to, now. It is getting difficult to lift the bricks onto the chimney stack. It is much easier to lift a brick over one's head if the brick starts from a lower position. An 8.5 pound brick lifted from head level feels much heavier than the same brick lifted from knee or waist height - try it if you don't believe me.

The photo on the left shows the chimney not in alignment with the rough cut hole in the shed roof. Looks like I will have to rent a Sawz-All to cut the hole bigger. Some more of the support wood needs to be cut, as well the aluminum roofing needs to have corners squared for the chimney bricks.

I checked into renting a "person"-lift to work above the kiln shed roof - obviously the blue ladder is not tall enough. And the 'lift' should extend over the roof edge to just where the bricks will come through the roof.