Wednesday, January 20, 2010

Some last touches


Today a few items got tied up on the kiln.

Photo on the left shows the pipes/plumbing for the propane. Yesterday, I met Howard at Lowe's to select the black iron nipples, bell reducers, tee's, an elbow and a cross. We laid out the pieces we wanted on the floor to make sure they were all there. Did very good, too, as there was one iron nipple left-over.

The green thingy is a pressure reducer for my raku kiln. My old gas kiln ran on low-pressure propane burners, the new kiln will run on hi-pressure propane burners. All the connections between the propane tank and the kiln burners themselves had been like a "black box" to my brain. The parts needed to get propane from point A to point B was a big mystery to me. I don't begin to "know it all" at this time, but I have greatly improved my understanding of how & why one uses particular pieces to "plumb" a kiln. And the raku kiln is now operable!

On the right side photo, the angle-iron braces on the sides of the upper chimney were installed today. The original design called for the braces to be longer, but they didn't fit with the rain flashing on the chimney above the roof. So we had Claude cut the angle-iron, and it was reconfigured as pictured above. Threaded tie rods go around the chimney at the top & bottom of the metal braces.

Time to go back to making pots - there's nearly enough for the first firing...

Kiln Door & more


The short story is the photo on the right. Soft bricks were mortared next to the corbelled chimney bricks and against the kiln wall. This is the only place on the side walls that did not have kaowool (fiber insulation) for added insulation.

On the left, is a brick-up of the kiln entrance. Hard bricks are next to the hot-face interior of the kiln, and soft bricks are the back-up layer. If you look close, you can see that I ran out of soft bricks half way up the doorway. I still have some soft bricks, but they all need to be mortared together. That means they are halves (or in more pieces). It took many tries of bricks going up and down to come up with what is pictured. To get the peep holes in position to line up with the holes cut in the sheet-metal/kaowool door cover was one obstacle.

I had not planned for the number of half bricks I would need in the door. Renting a brick saw, hauling it out here, then back to town just to cut a small number of bricks seemed like over-kill and a lot of time spent for a little amount to get done. Sutherlin Rentals was open on Monday's holiday, and consented to let me bring my bricks in to be cut. They knew me from previous rentals, and set up the brick saw in back. It didn't take me long to cut the bricks I needed (and a few spares). Not watching the time, I can't say for sure, but I'm sure it was not more than 15 minutes.

Thursday, January 14, 2010


Today, a brick mason, Randy, came to help me finish the chimney. He could definitely lay bricks much faster than I could. I learned a few brick-laying tricks now - at the end of my brick-laying.

The rain flashing as the chimney came through the roof seemed to be the greatest challenge to me. Randy knew what to do. We had many discussions, as I wanted to have much more air through the roof next to the chimney. Claude brought a can of spray rust-o-leum primer to protect the galvanized metal rain flashing.

The chimney now rises at least 24" above the roof. We ended up placing a board weighted down with a couple of bricks on top of the chimney to prevent rain from coming down the hole.

I keep making a few more pots for the kiln...

Saturday, January 2, 2010

Out of Mortar - Again


Thursday & Friday (New Year's Eve & Day) the chimney got mortared to within 10 rows of the kiln shed roof. The top row of bricks has only 3 of the 7 bricks mortared before the mortar ran out.

See how much higher than the blue ladder the chimney goes to, now. It is getting difficult to lift the bricks onto the chimney stack. It is much easier to lift a brick over one's head if the brick starts from a lower position. An 8.5 pound brick lifted from head level feels much heavier than the same brick lifted from knee or waist height - try it if you don't believe me.

The photo on the left shows the chimney not in alignment with the rough cut hole in the shed roof. Looks like I will have to rent a Sawz-All to cut the hole bigger. Some more of the support wood needs to be cut, as well the aluminum roofing needs to have corners squared for the chimney bricks.

I checked into renting a "person"-lift to work above the kiln shed roof - obviously the blue ladder is not tall enough. And the 'lift' should extend over the roof edge to just where the bricks will come through the roof.

Wednesday, December 30, 2009

Chimney on-the-way

Eight rows were mortared today - using the big ladder. There is a shelf on the ladder where the hinge is - and it is big enough for the bucket of mortar. This made building up the rows of bricks manageable.

I am watering down the little bit of mortar remaining - I hope it will last til just below the roof. Actually, there is no reason to use the full thickness of the mortar - I'm just trying to keep the bricks in place from heat & earthquakes. I've been thinning out the buckets of mortar for quite awhile, it is way too thick to work with. Even though I was told by the manufaxturer the mortar is "trowel ready", I wonder if that is for instances when there is a 1/2" or so of mortar between the bricks.
Anyway, it will take more arm muscle to raise the bricks to mortar them as I get closer to the roof.

I'm not sure what I will use to reach to place bricks above the roof. A scaffold was suggested to me, but I don't know that I can reach over the edge of the roof to reach the chimney even with that. It seems to me that a "cherry picker" lift would be the thing to use. I wonder how much one of those costs to rent for a day?

Saturday, December 26, 2009

No More Corbeling In





The left pic is the ledge in the chimney that supports the two dampers as they slide in & out from each side.

On the lower left is the same ledge with newspaper on a damper shelf to catch any stray mortar that would obstruct the free sliding of the dampers. As the chimney gets built up higher, I will not be able to see or clear the sliding ledge of debris. When all the chimney bricks are mortared, the shelf supporting the newspaper will be removed and the newspaper will fall to be burned when the kiln is fired up.

The upper center photo has 3 rows of chimney bricks laid out in the order they will be mortared. On the left side of that pic is the last chimney row that is corbelled in, and is also the top row in the right side photo. I found I needed to see & measure these 3 rows of bricks to know just how much to adjust the indent on the last corbel rows. From now on, every chimney row laid above those on the right photo will be 7 bricks each, until above the roof, when the rain guard is finally reached.

Today, I started using the taller ladder in the right photo. It is not going to last many more rows. I'll have to find a taller ladder - and it cannot be an extension ladder (that would lean on the chimney)! I'm also on the last 25% of the latest bucket of mortar. It seems to be a slim to zero chance that I have enough mortar to finish this project. I really want to mortar some rows of soft bricks around the bottom of the chimney. I wonder if my local brick supplier took my suggestion to purchase mortar from a particular in-state NorthWest manufacturer, rather than shipping it in from the mid-West at nearly triple the price.

Wednesday, December 23, 2009

More Chimney Bricks


You can see the chimney is getting higher. The close-up on the left shows the split bricks for the dampers' row. In the row below the dampers, the front & back chimney rows of bricks are moved in 1/2" to support the damper shelves. Of course, I forgot to indent the bricks on that row until I had finished mortaring them. So I had to get a chisel and move the bricks in. This is when the cool weather comes in handy: it was cold enough that the mortar had not set & I was able to move the bricks without too much trouble. I'm now within a few rows of no more corbeling - hoorah!